The Metro to Monterrey airport has a new date: February 2027. Governor Samuel García gave it on October 29, 2026, during the Index convention, saying Lines 4 and 6 will reach Monterrey International Airport that month. The previous goal, having at least one section running for the June 2026 World Cup, was not met.
The date should be read carefully. The announcement itself made it conditional on the works allowing the service to open, and it did not say which stations would open first. Here is what is confirmed about the route, the Aeropuerto station and construction progress.
What was announced and what was not
| Topic | Confirmed |
| Target date to the airport | February 2027, according to the governor (October 29, 2026). Subject to construction progress. |
| Lines | 4 and 6, both elevated monorail |
| Total project length | About 34 km between the two lines |
| Section to the airport | 8 km; 7 finished by mid-October |
| Civil works progress | 85%, according to Metrorrey (October 12, 2026) |
| Trains | 6 of 13 available |
| Fare and hours | Not announced |
The route: along Miguel Alemán to Apodaca
Lines 4 and 6 are the largest Metro expansion in Nuevo León’s history. They run on an elevated viaduct and cross over Line 1 at Y Griega station, where the viaduct reaches 24 meters in height.
Line 6 is the one that goes toward the airport. It follows Miguel Alemán avenue and crosses Guadalupe, San Nicolás de los Garza and Apodaca, the municipality where the airport is located. Among the most advanced stations are Churubusco, La Fe, Torre Administrativa and Bonifacio Salinas, according to construction reports this year.
In May 2025, when work on the Aeropuerto station began, the state government said that with the extension the two lines would total 34.37 kilometers and be the longest Metro line in Latin America.
The Aeropuerto station
Construction began on May 5, 2025. The project includes about 1,650 square meters of platforms, concourse, walkways and entrances, with an air-conditioned station, escalators and elevators. The government mentioned that its operation would take into account the times of the first flights of the day.
What is still unclear is how it will connect with the terminals. The airport has three separate buildings, A, B and C, and it has not been explained whether the station will reach one of them, whether there will be walkways to all three or whether the inter-terminal bus will be needed. For those traveling with luggage, that detail matters as much as the date.
Construction progress as of October 2026
On October 12, Abraham Vargas, director of Metrorrey, gave the latest detailed update: 85% progress on civil works, with the viaduct and stations above 90%. Taking all 21 stations together, overall progress was 60%.
On the airport section, seven of the eight kilometers were finished and about 900 meters of beams remained. On the electromechanical side there were 6 of the 13 trains needed and a second electrical substation still had to be installed, with its equipment arriving on October 20.
Vargas proposed opening in sections if the tests go well. In other words: the first service might not reach the airport yet.
The dates that were missed
- December 2023: the extension of Line 6 to the airport is announced.
- April 3, 2024: work on the extension begins.
- May 5, 2025: construction of the Aeropuerto station starts.
- Late April 2026: first monorail tests on a short section near La Fe.
- June 2026: the goal of opening a section for the World Cup is not met.
- October 29, 2026: the governor sets February 2027 to reach the airport.
Several pages that appear in search results still promise the Metro to the airport for June 2026. That information is no longer current.
How to get to the airport in the meantime
Today there is no Metro to the airport. The options are still an authorized taxi, your own car or public transport with transfers; they are described in the guide to public transport to Monterrey airport. If you are leaving your car, check the rates for Monterrey airport parking. Heading west? Options and prices are in our guide from Monterrey airport to San Pedro Garza García.
Before leaving, find your terminal on the Monterrey airport map: Viva leaves from C, Aeroméxico, Delta and American from B, and most others from A.
Frequently asked questions
When will the Metro reach Monterrey airport?
The Nuevo León government’s latest target is February 2027, announced on October 29, 2026 and conditional on construction progress.
Which Metro line goes to the airport?
Line 6, along Miguel Alemán avenue. The government presents the project together with Line 4; both are monorail.
How much will the fare cost?
It has not been announced. The government only said access will be by card or QR code.